Preparation:
Before applying this coating we advise that you vacuum the area. Old paint finishes should be removed if flaking at all and if well bonded abraded sanded to create texture prior to applying the paint. Preparing the floor mechanically (shot blasting or grinding) is always advisable but if that is not possible our Etch and Clean is a good alternative.
Application:
We advise when applying this product the ambient temperature is at least 7°C. Please note for 2 coats you will require 2 epoxy rollers.
1. Pour 100% of your part B tin in to part A
2. Mix resin components together with a drill and paddle for 1 minute
3. Pour content in to a paint scuttle
4. Immediately begin applying your paint with an epoxy roller frame and sleeve
5. Use a brush around the edges for a smooth finish (a second pair of hands comes in useful)
6. Once coat one has been applied leave 12-24 hours then apply second coat
PLEASE NOTE: The pot life of this product is 20 minutes. This means the paint will start to chemically cure after this time. Ensure you remove the paint from the tin in this window. The paint will then be workable on your floor for 40 minutes.
Pot life = Time to harden in pot following addition of hardener
Working Time = Time to apply product before becoming unworkable